After review, some blades will be removed, and others will be reinforced. The post Vineyard Wind is given the OK to move ...
Vineyard Wind early Wednesday morning revealed that it has been given approval to resume installation of turbine blades after ...
The project is removing some blades and "strengthening other blades as needed to support the safety and operational readiness ...
According to GE Vernova, the turbine blade failure was was caused by a "material or manufacturing deviation" at a factory in ...
A spokesperson said power production "will resume only after additional progress is made and all requisite approvals are ...
Vineyard Wind plans to remove an unspecified number of blades from existing turbines after conducting scans and quality ...
In a Sept. 27 letter addressed to Vineyard Winds’ chief executive and its director of permitting, the Bureau of Safety and ...
GE Vernova and Vineyard Wind have provided an update on the implementation of their Incident and Response and Action Plan, ...
GE Vernova will remove some turbine blades installed at the Vineyard Wind offshore wind farm off the coast of Massachusetts following quality checks prompted by the failure of a blade in July, the ...
Offshore turbine manufacturer GE Vernova says it is removing some previously installed Haliade-X turbine blades from the ...
It indicates to me that there appear to be more issues with more blades than just the one, and that’s as much as I know,” ...
The company said other blades had a “manufacturing deviation” similar to a blade that shattered in July off the coast of ...