After months of delay, Vineyard Wind announced it was given the OK to remove a damaged blade and complete its project south ...
Vineyard Wind early Wednesday morning revealed that it has been given approval to resume installation of turbine blades after ...
The project is removing some blades and "strengthening other blades as needed to support the safety and operational readiness ...
What Vineyard Wind needs to do before turning turbines south of Nantucket back on. The wind farm has been offline since a ...
Vineyard Wind plans to remove an unspecified number of blades from existing turbines after conducting scans and quality ...
Vineyard Wind plans to remove an unspecified number of blades from existing turbines after conducting scans and quality ...
GE Vernova and Vineyard Wind have provided an update on the implementation of their Incident and Response and Action Plan, ...
Offshore turbine manufacturer GE Vernova says it is removing some previously installed Haliade-X turbine blades from the ...
An accident at the high-profile Massachusetts project over the summer saw one of its blades detach and plunge into the ocean.
According to GE Vernova, the turbine blade failure was was caused by a "material or manufacturing deviation" at a factory in ...
GE Vernova will remove some turbine blades installed at the Vineyard Wind offshore wind farm off the coast of Massachusetts ...